[Bug 659790] Re: partial completion of the production order

 

I would like to add:
Even if we change the production quantity from "Change Qty" button, we have a production order for the specified quantity only !
In your case it would produce 5 products and state would be 'Ready to progress'. 
It behaves perfectly and this is quite normal.

Thanks.

-- 
partial completion of the production order
https://bugs.launchpad.net/bugs/659790
You received this bug notification because you are a member of C2C
OERPScenario, which is subscribed to OpenERP OpenObject.

Status in OpenObject Addons Modules: New

Bug description:
Hello.
May i have a procurement order to procure 10 "make to order" details. May the manufacturing was completed partially for some unexpected reason. 
Then i changed product quantity in production order to 5 ones.
I finished production and the procurement orders(10 details) changed its state to "ready".
Does it do as it should?