[Bug 655034] Re: Project : Progressbar of project should be updated based on task changes.
I think in the V6-RC1, there is a small error :
The description of the progressbar : Percent of tasks closed according
to the total of tasks todo
I think for the moment the calculation is based on time spent/time total
But the task can be done and the time spent not equal to the total time.
The problem of the amount in analytic account still persists
(cfr https://bugs.launchpad.net/openobject-addons/+bug/655034/comments/6)
--
Project : Progressbar of project should be updated based on task changes.
https://bugs.launchpad.net/bugs/655034
You received this bug notification because you are a member of C2C
OERPScenario, which is subscribed to OpenERP OpenObject.
Status in OpenObject Addons Modules: Confirmed
Bug description:
There is a regression in the last trunk version,
The progressbar of the project no longer progress when the tasks advance
There is too a problem with the link between analytic and task work.
I link a user with a product with timesheet module but when I fill in the task work, the amount of the analytic entries is 0
Laurent