c2c-oerpscenario team mailing list archive
-
c2c-oerpscenario team
-
Mailing list archive
-
Message #00977
[Bug 645245] Re: [trunk] fixed delivery date
** Changed in: openobject-addons
Status: In Progress => Fix Committed
--
[trunk] fixed delivery date
https://bugs.launchpad.net/bugs/645245
You received this bug notification because you are a member of C2C
OERPScenario, which is subscribed to OpenERP OpenObject.
Status in OpenObject Addons Modules: Fix Committed
Bug description:
from experts list
Dear Ferdinand,
i agree with you. In real projects i made experience that this leads
sometimes to confusion. The proposed field should be the date (point of
view) to
calculate retrospective order date, expected delivery date of purchase
orders (do we have this field?),
manufacturing date.
The field delivery lead time is imho onla to print on a quotation to a
customer the timeframe we expect to deliver
the goods to customers location.
Regards
Thorsten
2010/9/6 Ferdinand Gassauer <office@xxxxxxxxxx>
> Hello!
>
> just wondered how to enter a fixed delivery date for a sel order or sale
> order
> line
>
> the client requests: "please deliver Sept 15th"
> today (sept 6th) I would have to enter delivery lead time 11 days - may be
> taking into account company.security_lead
>
> IMHO we need a requested delivery_date (even time for certain business)
> Opinions?
>