[Bug 496501] Re: Wrong computation of end time in Manufacturing operations when defining a working time
** Changed in: openobject-addons
Status: New => Triaged
--
Wrong computation of end time in Manufacturing operations when defining a working time
https://bugs.launchpad.net/bugs/496501
You received this bug notification because you are a member of C2C
OERPScenario, which is subscribed to the OpenERP Project Group.
Status in OpenObject Addons Modules: Triaged
Bug description:
5.0.7
Using the demo data I juste added the following
I have a Manufacturing Order of 10 C products ( C = A +B) using a routing of 2 hours
in the Assembly line
That gives me a manufacturing operation of 20 hours
If I don't assign a working time to the Assembly line it works fine
If I assign a Working time "Monday Only " to Assembly Line
with Monday Only defined as Monday from 08:00 to 18:00
The Manufactuing Operation planned dates are the SAME for start and end time