[Bug 689868] Re: Report "product cost structure" doesnt calculate components costs
This is with C declared as phantom in A, and D declared as phantom in C
and so on, or am I misunderstanding?
With phantom, I DO AGREE the cost calculation will be OK.
BUT in my process, it shall NOT be phantom, I do NOT want purchase
orders to be produced at once for all sub-sub-sub-sub-products needed,
it'll be unnecessarily confusing.
If it's possible to reach you directly, maybe it'll be easier and
quicker to understand each other per phone, I've got the feeling we
don't exactly talk about the same thing...
Anyhow, thanks for considering my issue.
--
You received this bug notification because you are a member of C2C
OERPScenario, which is subscribed to the OpenERP Project Group.
https://bugs.launchpad.net/bugs/689868
Title:
Report "product cost structure" doesnt calculate components costs
Status in OpenObject Addons Modules:
Invalid
Bug description:
Products A, B, C and D.
standard prices are 1€.
BoM for Product A: 1B + 4C
BoM for product B: 10D
(so one A should be composed of 10D + 4B, and in fact that's what the procurement orders do)
When calculating A's "product cost structure" report,
------------ I'm awaiting:
Costs A :
1 x costs B
10 x costs D = 10 x 1€
4 x costs C = 4 x 1 €
Total costs for one A : 14€
------------ BUT INSTEAD OF THIS, IT ...
... calculates A costs using A's BoM (A= 1B + 4C)
... doesn't calculate B's costs using B's BoM (B=10D).
Instead of this, creates a new B's "BoM components", with no other products in it.
Cost of one B = 1 x standard price of B = 1€
Costs A = 1x standard price of B + 4x standard price of C = 1€ + 4€ = 5€
------------ Note:
The report "BoM structure" is correct, it gives :
A
1B
10D
4C
Thanks in advance for correcting this bug (or for explanation if I'm understanding something wrong)