Hello,
The problem is when in the task the "Assigned to" field is left blank,
in GTK appears but not in web. When it is assigned to anyone the task
appears in both.
Colors: if it is not assigned to anyone, in GTK appears in red, in web
it appears in red when is assigned to anyone that is not the logged user
(in this case in the GTK appears in pink)
Regards
--
You received this bug notification because you are a member of C2C
OERPScenario, which is subscribed to the OpenERP Project Group.
https://bugs.launchpad.net/bugs/702247
Title:
Project_* : Calendar View not synchronized in GTK and Web Client.
Status in OpenERP Web Client:
Confirmed
Bug description:
We found the following problem with the Calendar view of the Project
Module :
Steps to Produce Bug:
- Create Project Foo: with starting
Now Click to to Shortcuts(Link) on Right Side panel "Task"
+ Create New Task "bar1" with Planned hour :150 Hours
+ Create New Task "bar2" with Planned hour :20 Hours
and start both Tasks
> Issue 1: Now Switch to calendar View and Check the calendar View with GTk Client and Web-Client they are producing different result.(same calendar behavior can be observed Phase scheduling, Project Issue. it is showing different scheduling in GTk and Web-Client)
> Issue 2:In web client : Project From view when i click to the Shortcut(Link) "Task" Left Side Panel, it will open new Tab in browser but in new tab what i observed is Left Side Panel changed to "Sale" Menu instead Project, weired.
Thank You