[Bug 730191] Re: Working times being ignored by workcenters for scheduling
I downloaded the trunk client-web version (6.1), and it appears to
possibly be a combination problem.
The gantt chart now shows 8 hour workdays, however it is still
scheduling days that are not on the assigned 'working times' list - i.e.
weekends.
--
You received this bug notification because you are a member of C2C
OERPScenario, which is subscribed to the OpenERP Project Group.
https://bugs.launchpad.net/bugs/730191
Title:
Working times being ignored by workcenters for scheduling
Status in OpenERP Server:
New
Bug description:
Tried on both 5.0.15 and 6.0.1 -
Using OpenERP to schedule manufacturing in a machine shop
I've setup working times of Monday-Friday, 07:00 thru 15:00
Created my workcenters, assigned the working time to them.
Create routings of approximately 7 workcenters in length.
Create a BOM which assigns a routing to a particular product.
Create a manufacturing order. Check the schedule -
If, for instance, I have a manufacturing operation with 16 hours, it
loads a single day with 16 hours, rather than breaking it up to 2
days.
It also ignores non-work days (Sat and Sun)
This is with mrp_operations and JIT scheduling installed (not sure
which is causing this issue).
I wouldn't exclude the possibility that I'm doing something wrong, but
this is the only real hurdle from having a functional scheduling
system for my shop, and it's a big one.
I'm open to workarounds if there are any.