[Bug 730190] Re: Working times being ignored by workcenters for scheduling
I had reassigned this to Openerp web client project, as it appears to be
a reporting/gantt chart issue. Unfortunately it seems that when I
reassign, it actually creates a new bug, so I apologize if it appears
like I'm spamming. As I did more testing yesterday, more details
became apparent to me.
Work order detail appears to show proper scheduled start and stop times,
but it's the gantt chart which displays it incorrectly - in 6.01 it
ignores working times entirely, in 6.1 (trunk) it respects working
hours, but schedules non-scheduled days.
--
You received this bug notification because you are a member of C2C
OERPScenario, which is subscribed to the OpenERP Project Group.
https://bugs.launchpad.net/bugs/730190
Title:
Working times being ignored by workcenters for scheduling
Status in OpenERP Modules (addons):
New
Bug description:
Tried on both 5.0.15 and 6.0.1 -
Using OpenERP to schedule manufacturing in a machine shop
I've setup working times of Monday-Friday, 07:00 thru 15:00
Created my workcenters, assigned the working time to them.
Create routings of approximately 7 workcenters in length.
Create a BOM which assigns a routing to a particular product.
Create a manufacturing order. Check the schedule -
If, for instance, I have a manufacturing operation with 16 hours, it
loads a single day with 16 hours, rather than breaking it up to 2
days.
It also ignores non-work days (Sat and Sun)
This is with mrp_operations and JIT scheduling installed (not sure
which is causing this issue).
I wouldn't exclude the possibility that I'm doing something wrong, but
this is the only real hurdle from having a functional scheduling
system for my shop, and it's a big one.
I'm open to workarounds if there are any.