[Bug 726185] Re: [6stab] long term scheduling doesn't work across projects
** Changed in: openobject-addons
Importance: Undecided => Wishlist
** Changed in: openobject-addons
Status: New => Confirmed
** Changed in: openobject-addons
Assignee: (unassigned) => OpenERP R&D Addons Team 1 (openerp-dev-addons1)
--
You received this bug notification because you are a member of C2C
OERPScenario, which is subscribed to the OpenERP Project Group.
https://bugs.launchpad.net/bugs/726185
Title:
[6stab] long term scheduling doesn't work across projects
Status in OpenERP Modules (addons):
Confirmed
Bug description:
When you have two projects with two phases each. Every phase has two
tasks. You have only one the same resource for all tasks in both
projects. This resource is in Resource Allocation in all phases. And
user for the resource is a member of both projects. The resource-user
has Working period from standard demo data. So it is only one
resource-user for all 8 tasks. When you make "Compute Phase
Scheduling" for all projects the system schedules for the same time
tasks from two projects for the same resource-user. Scheduling works
correctly only within project. Scheduling doesn't see that resource-
user is busy on another project task.