[Bug 730191] Re: Working times being ignored by workcenters for scheduling

 

*** This bug is a duplicate of bug 730190 ***
    https://bugs.launchpad.net/bugs/730190

** This bug has been marked a duplicate of bug 730190
   Working times being ignored by workcenters for scheduling
 * You can subscribe to bug 730190 by following this link: https://bugs.launchpad.net/openobject-client-web/+bug/730190/+subscribe

-- 
You received this bug notification because you are a member of C2C
OERPScenario, which is subscribed to the OpenERP Project Group.
https://bugs.launchpad.net/bugs/730191

Title:
  Working times being ignored by workcenters for scheduling

Status in OpenERP Web Client:
  New

Bug description:
  Tried on both 5.0.15 and 6.0.1 -

  Using OpenERP to schedule manufacturing in a machine shop

  I've setup working times of Monday-Friday, 07:00 thru 15:00

  Created my workcenters, assigned the working time to them.

  Create routings of approximately 7 workcenters in length.

  Create a BOM which assigns a routing to a particular product.

  Create a manufacturing order.  Check the schedule -

  If, for instance, I have a manufacturing operation with 16 hours, it
  loads a single day with 16 hours, rather than breaking it up to 2
  days.

  It also ignores non-work days (Sat and Sun)

  This is with mrp_operations and JIT scheduling installed (not sure
  which is causing this issue).

  I wouldn't exclude the possibility that I'm doing something wrong, but
  this is the only real hurdle from having a functional scheduling
  system for my shop, and it's a big one.

  I'm open to workarounds if there are any.