[Bug 770392] Re: date issue with sales flow

 

Hello,

This is not a bug, but the demo data should be improved, for example
lead time for products = 5 days, and security days = 1.

And for the all product the delivery lead time should be grater then the
supplier lead time for example in pc1 there is a delivery lead time is 2
days this should be increased to 7 or more.

Thanks.

** Changed in: openobject-addons
   Importance: Undecided => Low

** Changed in: openobject-addons
       Status: New => Confirmed

** Changed in: openobject-addons
     Assignee: (unassigned) => OpenERP R&D Addons Team 2 (openerp-dev-addons2)

-- 
You received this bug notification because you are a member of C2C
OERPScenario, which is subscribed to the OpenERP Project Group.
https://bugs.launchpad.net/bugs/770392

Title:
  date issue with sales flow

Status in OpenERP Modules (addons):
  Confirmed

Bug description:
  Hi,

  While doing labs on Warehouse, I find that there is a date issue in
  sales flow. First create a new SO with ordered date of current date
  (for ex, 26/Apr). After confirm this SO, it will create Delivery Order
  with Ordered Date of 25/Apr, Expected (Scheduled Date) Date of 22/Apr.
  I think it should be some date in future such as 28/Apr due to lead
  time. Instead, it's back to the past. I think it's a bug.

  Regards,