[Bug 791350] Re: Sub Contracting Manufacturing Stock Moves
Hello,
I have checked the issue once again and according to OpenERP system it supports partial Sub contracting in manufacture.
When you create a main product which has sub product in it, at the time of creation of its BOM we have to specify the routing and production location in which we have to specify the same location for "chained location if fixed" as the "finished production location".
So when you create MO of the main product it will have routing as
defined at the time of BOM.
I have attached a video for your reference which shows how the stock
moves.
Thank you and waiting for your reply.
--
You received this bug notification because you are a member of C2C
OERPScenario, which is subscribed to the OpenERP Project Group.
https://bugs.launchpad.net/bugs/791350
Title:
Sub Contracting Manufacturing Stock Moves
Status in OpenERP Modules (addons):
Invalid
Bug description:
I try to do Sub Contracting Manufacturing. The case is I am going to deliver material to partner and they are going to produce and ship the material back to me.
But when we start the production order for the main Product which has this Sub Contracting Assembly then what OpenERP currently doing is-
1. Creates Delivery Order for all the RAW materials -- this is correct
2. Once I confirm the Delivery Order it creates Incoming Shipments of all the RAW materials again.?? BUG BUG
It should create incoming shipment with the finished assembly and not
the RAW materials again.
Please let me know about the same. I am using OpenERP 6.0.2
Sid