[Bug 772724] Re: [project] If one task is done, error on re-scheduling Tasks
Hello,
As per the comment #4 (2. Child task has to be done before parent task) we have made the changes and this change will automatically restrict the message not appear as we are now preserving parent child dependency for task. and Fix has been committed to the lp:~openerp-dev/openobject-addons/trunk-bug-772724-jam and will be soon merged to trunk addons.
Thanks all for your support.
** Changed in: openobject-addons
Status: In Progress => Fix Committed
** Branch linked: lp:~openerp-dev/openobject-addons/trunk-bug-772724-jam
--
You received this bug notification because you are a member of C2C
OERPScenario, which is subscribed to the OpenERP Project Group.
https://bugs.launchpad.net/bugs/772724
Title:
[project] If one task is done, error on re-scheduling Tasks
Status in OpenERP Modules (addons):
Fix Committed
Bug description:
System: Ubuntu 10.10. OERP 6.0.2. Fresh db, with Project and Long term
planning installed.
I made a new project with 45 hr/week Working time (9hr/day with 1 hour lunch time), starting at 25 April, 2011.
I made 2 tasks: Task1 (planned hour: 9 hr), Task2 (36 hr). Task2's parent is Task1.
After Compute Task Scheduling, everything is OK (https://bugs.launchpad.net/bugs/768889,
https://bugs.launchpad.net/bugs/771161).
I start working on Task1 and I ran out of time (9hrs) and I succeed with 2 extra hours. So I modify the Ending date of Task1 to be 26/04/2011 10:00. I click on Done to consider finished this Task.
But before I start Task2, I wand to re-schedule the project task's because Task1 had a 2 hr. delay.
Here I get this error message: 'Task_9' is not a valid attribute of
'root'
I tried to put Task2 in open state and only after get the re-schedule,
but the same.
Thank you