[Bug 772724] Re: [project] If one task is done, error on re-scheduling Tasks

 

** Changed in: openobject-addons
       Status: Fix Committed => Fix Released

-- 
You received this bug notification because you are a member of C2C
OERPScenario, which is subscribed to the OpenERP Project Group.
https://bugs.launchpad.net/bugs/772724

Title:
  [project] If one task is done, error on re-scheduling Tasks

Status in OpenERP Modules (addons):
  Fix Released

Bug description:
  System: Ubuntu 10.10. OERP 6.0.2. Fresh db, with Project and Long term
  planning installed.

  I made a new project with 45 hr/week Working time (9hr/day with 1 hour lunch time), starting at 25 April, 2011.
  I made 2 tasks: Task1 (planned hour: 9 hr), Task2 (36 hr). Task2's parent is Task1.
  After Compute Task Scheduling, everything is OK (https://bugs.launchpad.net/bugs/768889,
  https://bugs.launchpad.net/bugs/771161).

  I start working on Task1 and I ran out of time (9hrs) and I succeed with 2 extra hours. So I modify the Ending date of Task1 to be 26/04/2011 10:00. I click on Done to consider finished this Task. 
  But before I start Task2, I wand to re-schedule the project task's  because Task1 had a 2 hr. delay. 

  Here I get this error message: 'Task_9' is not a valid attribute of
  'root'

  I tried to put Task2 in open state and only after get the re-schedule,
  but the same.

  Thank you