[Bug 808602] Re: [trunk][purchase]Scheduled date in past when lead time is one day
In the case of MTS, the scheduled date must take into account the
company lead time otherwise the date for the purchase order is wrong
For MTS only:
Procurement Scheduled Date = Today + Supplier Delivery Lead Time + Company Purchase Lead Time
--
You received this bug notification because you are a member of C2C
OERPScenario, which is subscribed to the OpenERP Project Group.
https://bugs.launchpad.net/bugs/808602
Title:
[trunk][purchase]Scheduled date in past when lead time is one day
Status in OpenERP Modules (addons):
New
Bug description:
My scenario:
Supplier has a one day lead time for all material order prior to 2PM the previous day. So I set Purchase delay to 0 on the company form and supplier delay to 1 on the product form. The product is MTS with a automatic orderpoint configured.
Result:
The orderpoint generated purchase order is one day in the past.
It also appears that you cannot use a delay of 0, though this wouldn't really make sense in this scenario.
I'm not sure the way the requested date works makes sense either - it appears that the formula for requested date is PO sched'd date - seller delay. Why would the request date include the seller delay, shouldn't that only be used for internal calculation? If a seller has a delay of 10 days and I want something 10 days in the future, it puts a req'd date of today?