[Bug 812794] Re: purchase : wrong scheduled date and order date for PO generated from procurement
** Description changed:
The order date and scheduled date of the PO is wrong.
Currently:
The PO order date = today
- The PO order line scheduled date = procurement scheduled date - supplier lead time - purchase lead time
+ The PO order line scheduled date = procurement scheduled date - supplier lead time - company purchase lead time
Must be:
- The PO order date = procurement scheduled date - supplier lead time - purchase lead time
- The PO order line scheduled date = procurement scheduled date
+ The PO order date = procurement scheduled date - supplier lead time - company purchase lead time
+ The PO order line scheduled date = procurement scheduled date - company purchase lead time
** Description changed:
The order date and scheduled date of the PO is wrong.
Currently:
- The PO order date = today
- The PO order line scheduled date = procurement scheduled date - supplier lead time - company purchase lead time
+ PO order date = today
+ PO order line scheduled date = procurement scheduled date - supplier lead time - company purchase lead time
Must be:
- The PO order date = procurement scheduled date - supplier lead time - company purchase lead time
- The PO order line scheduled date = procurement scheduled date - company purchase lead time
+ PO order date = procurement scheduled date - supplier lead time - company purchase lead time
+ PO order line scheduled date = procurement scheduled date - company purchase lead time
--
You received this bug notification because you are a member of C2C
OERPScenario, which is subscribed to the OpenERP Project Group.
https://bugs.launchpad.net/bugs/812794
Title:
purchase : wrong scheduled date and order date for PO generated from
procurement
Status in OpenERP Modules (addons):
New
Bug description:
The order date and scheduled date of the PO is wrong.
Currently:
PO order date = today
PO order line scheduled date = procurement scheduled date - supplier lead time - company purchase lead time
Must be:
PO order date = procurement scheduled date - supplier lead time - company purchase lead time
PO order line scheduled date = procurement scheduled date - company purchase lead time