[Bug 838249] Re: project task - bizarre calculation of total hours

 

Hello Dr Ferdinand,

I have checked your issue but it is not a bug.

I think may be you have misunderstand something, If your 'Time Spent"
(working hours) is  greater then the planned hours then Remaining Hours
will be always in negative because

 Planned Hours =  Time Spent  + Remaining Time

Form your scenario you have planned 8 hours than you have worked 14 hours so  Remaining Hours will become -6 and which is correct.
Time Spent (14) + time remaining (-6) = (8)Planned Hours.

So Currently I am closing this issue.
Hope this will help for you.

Correct me if I am wrong.

Thanks.

** Changed in: openobject-addons
       Status: New => Invalid

** Converted to question:
   https://answers.launchpad.net/openobject-addons/+question/169880

-- 
You received this bug notification because you are a member of C2C
OERPScenario, which is subscribed to the OpenERP Project Group.
https://bugs.launchpad.net/bugs/838249

Title:
  project task - bizarre calculation of total hours

Status in OpenERP Modules (addons):
  Invalid

Bug description:
  total hours computation
  IMHO remaining hours should only be added if these are positive.

  and yes - the planned hours  should be reevaluated to avoid negative
  remaining hours.