Hello Dr Ferdinand,
I have checked your issue but it is not a bug.
I think may be you have misunderstand something, If your 'Time Spent"
(working hours) is greater then the planned hours then Remaining Hours
will be always in negative because
Planned Hours = Time Spent + Remaining Time
Form your scenario you have planned 8 hours than you have worked 14 hours so Remaining Hours will become -6 and which is correct.
Time Spent (14) + time remaining (-6) = (8)Planned Hours.
So Currently I am closing this issue.
Hope this will help for you.
Correct me if I am wrong.
Thanks.
** Changed in: openobject-addons
Status: New => Invalid
** Converted to question:
https://answers.launchpad.net/openobject-addons/+question/169880
--
You received this bug notification because you are a member of C2C
OERPScenario, which is subscribed to the OpenERP Project Group.
https://bugs.launchpad.net/bugs/838249
Title:
project task - bizarre calculation of total hours
Status in OpenERP Modules (addons):
Invalid
Bug description:
total hours computation
IMHO remaining hours should only be added if these are positive.
and yes - the planned hours should be reevaluated to avoid negative
remaining hours.