[Bug 885647] Re: project : Field total_hours calculates wrong time
** Changed in: openobject-addons
Status: Confirmed => In Progress
--
You received this bug notification because you are a member of C2C
OERPScenario, which is subscribed to OpenERP Project Group.
https://bugs.launchpad.net/bugs/885647
Title:
project : Field total_hours calculates wrong time
Status in OpenERP Addons (modules):
Fix Committed
Bug description:
step 1:
Create new project
step 2:
Create Task 1 for this project and eg. Assign Planned Hours 10. it should be 10
Now see Project List View > Planned time will be 10 and Total Time
will be 00
Step 3:
Create Task 2 for this Project and eg. Assign Planned Hour 20
Now see Project List View > Planned time will be 30 and Total Time
will be 10. it should be 30
Step 4:
if we start any of Task then Total Time of project will be 30
To manage notifications about this bug go to: