[Bug 909666] Re: Purchase Expected Date

 

** Description changed:

  When make manual Purchase and add Product to PO then expected date (for full PO) and scheduled date (for PO line) calculate correct: scheduled date = current date plus Delivery Lead Time (from Product); expected date = min(scheduled dates).
- But when make automate Purchase through Procurement then in new PO scheduled dates (for PO lines) calculate wrong: scheduled date = current date plus 1 day.
+ But when make automate Purchase through Procurement (Sales Order) then in new PO scheduled dates (for PO lines) calculate wrong: scheduled date = current date plus 1 day. And auto Purchase from manual Procurement: scheduled date = current date minus 7 day (here like Delivery Lead Time = 7).
  Product - Stockable, MTO, Buy.

-- 
You received this bug notification because you are a member of OpenERP
Framework Experts, which is subscribed to OpenERP Addons.
https://bugs.launchpad.net/bugs/909666

Title:
  Purchase Expected Date

Status in OpenERP Addons (modules):
  New

Bug description:
  When make manual Purchase and add Product to PO then expected date (for full PO) and scheduled date (for PO line) calculate correct: scheduled date = current date plus Delivery Lead Time (from Product); expected date = min(scheduled dates).
  But when make automate Purchase through Procurement (Sales Order) then in new PO scheduled dates (for PO lines) calculate wrong: scheduled date = current date plus 1 day. And auto Purchase from manual Procurement: scheduled date = current date minus 7 day (here like Delivery Lead Time = 7).
  Product - Stockable, MTO, Buy.