[Bug 911806] Re: uom conversion between mrp.production and mrp.bom

 

*** This bug is a duplicate of bug 894624 ***
    https://bugs.launchpad.net/bugs/894624

** This bug has been marked a duplicate of bug 911775
   Manufacturing order UOM bug

-- 
You received this bug notification because you are a member of OpenERP
Framework Experts, which is subscribed to OpenERP Addons.
https://bugs.launchpad.net/bugs/911806

Title:
  uom conversion between mrp.production and mrp.bom

Status in OpenERP Addons (modules):
  New

Bug description:
  hi,

  To reproduce

  1. create 2 products:
  Final product, UoM: kg
  Base product, UoM: tonne

  2. create a BoM for Final product
  quantity: 1, Uom: tonne (!)
  that uses
  Base product, quantity: 1, UoM: kg (!)

  3. create a production order for Final product
  quantity: 1
  UoM: kg

  4. confirm it

  Expected "products to consume":
  Base product: 0.001 kg

  Got:
  Base product: 1000 kg = 1 tonne

  An alternative and similarly buggy scenario is to change the BoM line for Base product from kg to tonne. That is 1 tonne Base product creates 1 tonne of Final product.
  Then when producing 1 kg Final product we need 1000 tonne of Base product, instead of 1 kg.