Hi Paul,

Hopefully, it is fixed now. You had one period from 2009-09-01 to 2009-09-30
and another one from 2009-09-30 to 2009-10-30.
I deleted the second one, as there were no data for that period.

I wonder how this happened, something to do with the import of data perhaps?
Didn't you have exactly the same problem earlier, too? It would be good to
know how something like this can happen in DHIS2, it seems to be a bug,
perhaps with the import process.

Knut

On Wed, Jan 20, 2010 at 9:06 PM, Paul Amendola <Paul.Amendola@xxxxxxxxxx>wrote:

>  Hi Knut
>
>
>
> Hanks again for all of the help. On one of the instances [
> 109.74.202.200:8080/irc] the period Sept 2009 is repeated. Its been a
> little bit of a problem in the analysis. Do you know of any way to delete
> the extra period?
>
>
>
> Thanks
>
> Paul
>



-- 
Cheers,
Knut Staring