Scheduled aggregation

 

Hi,
we're currently reviewing how DHIS2 is used for the yearly review here in Ghana, and an issue related to the aggregation came up: during the reviews, which go into February and March, data quality issues with the previous years data are often found, and needs to be corrected. However, since only the last 12 months are aggregated by the scheduled datamart, changes made to the data in January and February are never reflected in the reports for the previous year unless the datamart is run manually. 

Perhaps the scheduler could either let 
1) set the number of months to aggregate daily/weekly
2) increase the aggregation to for example 14 months instead of 12
??

Olav