Dear Lars,
To edit program stage in DHIS2,I am facing the problem,system does not showing "Available data elements" list.
Barnali Banerjee
________________________________
From: Lars Helge Øverland <larshelge@xxxxxxxxx>
To: Rodolfo Melia <rmelia@xxxxxxxxxxxx>
Cc: Barnali Bhaduri <barnali760@xxxxxxxxxxx>; "dhis2-devs@xxxxxxxxxxxxxxxxxxx" <dhis2-devs@xxxxxxxxxxxxxxxxxxx>
Sent: Wednesday, 10 April 2013 9:31 PM
Subject: Re: [Dhis2-devs] Requirement
Hi Barnali,
it would be good if could provide some more info re your problem, like the aggregation query, potential exceptions - makes it easier to help.
regards,
Lars
On Tue, Apr 9, 2013 at 9:31 PM, Rodolfo Melia <rmelia@xxxxxxxxxxxx> wrote:
Sometimes, if you are simply counting encounters or similar, you may not even need to set a condition. If you set a condition, then it must be a full logical statement, like gender='female'.
>
>
>
>On Tue, Apr 9, 2013 at 8:10 PM, Barnali Bhaduri <barnali760@xxxxxxxxxxx> wrote:
>
>Hi,
>> Thank you very much.
>> I have one requirement,related to aggregation query builder using single event without registration program data element.I try to follow DHIS2 user guide ,but it is not clear to me,when I try to follow the step,the test condition not run successfully .From where I get the result.
>>
>>Thanks
>>
>>Barnali Banerjee
>>
>>
>>________________________________
>> From: Rodolfo Melia <rmelia@xxxxxxxxxxxx>
>>To: Barnali Bhaduri <barnali760@xxxxxxxxxxx>
>>Cc: "dhis2-devs@xxxxxxxxxxxxxxxxxxx" <dhis2-devs@xxxxxxxxxxxxxxxxxxx>
>>Sent: Monday, 8 April 2013 2:00 PM
>>Subject: Re: [Dhis2-devs] Requirement
>>
>>
>>
>>Hi - you seem to want to use the system for recording individual transactions, rather than data reported in a pre-stablished interval using a recurrent reporting frequency. Perhaps you should use Single Event without registration?
>>
>>
>>Regarding your UI requirements, you can create a custom form that could incorporate jscript, so you can achieve what you describe in your email.
>>
>>
>>R
>>
>>
>>
>>On Sun, Apr 7, 2013 at 8:24 AM, Barnali Bhaduri <barnali760@xxxxxxxxxxx> wrote:
>>
>>Dear All,
>>>We have the following requirement for an data element. Please let me know what will be the best way to implement it in DHIS2
>>>
>>>
>>>
>>>Say the aggregate data element is ABC for a facility, Facility 1
>>>
>>>
>>>1. On the 1st date (the day when the system starts) for a Facility the
Admin Facility Staff will enter initial current value of ABC in a data
entry form (UI-1). Say the initial value is X.
>>>
>>>
>>>This form will be entered
>>>1. On the first day of implementation
>>>2. Once in a while when required to manually override the value of ABC
>>>Facility staff will rarely use UI-1
>>>
>>>
>>>
>>>Nice to Have requirement:
>>>When the form is edited it will be great to have a time-stamped history of this record only if the system automatically does it
>>>.
>>>We will not like to have any "Frequency" (Period) , that needs to be manually selected. But as it
seems a required field, we can make the Frequency Yearly. If that is the case, is it possible to have a job that will copy the value of ABC of
2013 to 2014 at mid-night of 31st December, 2013 automatically?
>>>
>>>
>>>2. Ongoing basis the Facility Staff at the Front desk (different from the
admin staff), will be using another form (UI-2) to increment ABC by 1,
with a single click
>>>
>>>
>>>The initial ABC value will come from the UI 1. Say, it is X.
>>>
>>>
>>>It will have the following layout
>>>ABC = _X__ (not editable) [Increment Button by 1]
>>>The facility staff will click on the increment button. With one click the value of ABC will become X + 1.
>>>
>>>
>>>The facility staff may do this click once, more then once or not at-all on a single day. It is not required to capture the time-stamp of these
clicks.
>>>
>>>
>>>
>>>The requirement is that the staff entry will be ONLY in the form of clicking the buttons, nothing else.
>>>There should be minimal amount of manual data entry required in this screen. If any data is required (e.g: Organization Unit) it should be only a
single value and defaulted by the system (e.g: Organization Unit
defaulted to Facility 1)
>>>
>>>
>>>The basic idea of the requirement is as following:
>>>
>>>1. The facility admin wants to make this easier for the staff as much as possible while wants to keep the duty segregated.
>>>
>>>2. They want to have two UI, one for initialization and manual override and other for one click update (not editable)
>>>3. They are not so concerned about the reporting part. It is good to have
the audit , history etc to understand the performance of staff, but not
at the expense of making it difficult for the staff in their already
burdened day.
>>>
>>>
>>>Thanks
>>>
>>>Barnali Banerjee
>>>_______________________________________________
>>>Mailing list: https://launchpad.net/~dhis2-devs
>>>Post to : dhis2-devs@xxxxxxxxxxxxxxxxxxx
>>>Unsubscribe : https://launchpad.net/~dhis2-devs
>>>More help : https://help.launchpad.net/ListHelp
>>>
>>>
>>
>>
>>
>>--
>>
>>Rodolfo Meliá
>>Principal
>>rmelia@xxxxxxxxxxxx
>>www.knowming.com
>>+1 708 872 7636
>>+44 777 576 4090
>>Skype: rod.melia
>>Twitter: @RodolfoMelia
>>
>>
>>Note: Please note my new email address, which I will be using for PSI related work: rmelia@xxxxxxxxxxxx
>>
>>
>
>
>
>--
>
>Rodolfo Meliá
>Principal
>rmelia@xxxxxxxxxxxx
>www.knowming.com
>+1 708 872 7636
>+44 777 576 4090
>Skype: rod.melia
>Twitter: @RodolfoMelia
>
>
>Note: Please note my new email address, which I will be using for PSI related work: rmelia@xxxxxxxxxxxx
>_______________________________________________
>Mailing list: https://launchpad.net/~dhis2-devs