Hi Greg,

The uid J16EIqxFAau,  which we saw in
http://localhost:8080/dhis/api/system/tasks/AGGREGATE_QUERY_BUILDER?lastId=J16EIqxFAau,
is not the uid of any aggregate query builder defined.

It is a notification uid which is used as information of execute progress.

.....................................

Best regards,
Tran Chau.


On Mon, Mar 2, 2015 at 2:36 PM, Greg Rowles <greg.rowles@xxxxxxxxx> wrote:

> Hi Devs/Tran
>
> I stumbled across this page somehow but I cannot locate an object with uid
> value "WFQCq1dDkd1". How do I dig in further?
>
> [image: Inline image 1]
>
> On Sun, Mar 1, 2015 at 8:09 PM, Greg Rowles <greg.rowles@xxxxxxxxx> wrote:
>
>> Hi Devs/Tran
>>
>> Does any of the following make sense to you? Aggregations still fail but
>> I have better error info:
>>
>> [image: Inline image 1]
>>
>> FYI - I cannot locate the Aggregation Query Builder "J16EIqxFAau". It's
>> not in the current list (I check each one's details and none have that
>> id). Here is a different screenshot (each aggregate_query_builder error
>> references the same "J16EIqxFAau" id:
>>
>> [image: Inline image 2]
>>
>> Any suggestions?
>>
>> Regards,
>> Greg
>>
>>
>> On Fri, Feb 27, 2015 at 3:28 PM, Greg Rowles <greg.rowles@xxxxxxxxx>
>> wrote:
>>
>>> Thank you Tran
>>>
>>> We'll start testing ASAP... when we figure it out - we'll explain...
>>>
>>> Best,
>>> Greg
>>>
>>>
>>> On Fri, Feb 27, 2015 at 1:35 PM, Tran Chau (HISP Vietnam) <
>>> tran.hispvietnam@xxxxxxxxx> wrote:
>>>
>>>> Thank Greg,
>>>>
>>>> I tried creating a formula as your simple formula and chose the Task
>>>> strategy as 6 months, the data is generated and saved ok for 6 months in my
>>>> side. Please see the attachment snapshots.
>>>> I guess maybe data in your database got some issues.
>>>>
>>>> Besides, when Task strategy is changedd from  "12 months" to "6
>>>> months", we have to click *Stop *button and *Start *button before
>>>> clicking on *Execute *button. If not, the system will run with the old Task
>>>> strategy which we did set when we start *Schedule automated
>>>> aggregation* before.
>>>>
>>>> .................................
>>>> Best regards,
>>>> Tran Chau
>>>>
>>>>
>>>> On Thu, Feb 26, 2015 at 10:31 PM, Greg Rowles <greg.rowles@xxxxxxxxx>
>>>> wrote:
>>>>
>>>>> Hi Tran
>>>>>
>>>>> The schedule was changed from "12 months" to "6 months" but we are
>>>>> testing aggregation outcomes using the "Execute" command (most of the time
>>>>> it just hangs with "504 (Gateway Time-out)" and we also noticed the same
>>>>> for "Manual Aggregation", preview & save options). Our basic formulas use
>>>>> [Visited selected program stage] criteria while we have a set using more
>>>>> complex DateDiff() formulas. We know we have tracker data starting in
>>>>> Aug-2014 up till a few minutes ago:
>>>>>
>>>>> [image: Inline image 1]
>>>>>
>>>>>
>>>>> Complex Query:
>>>>>
>>>>> [image: Inline image 2]
>>>>>
>>>>> Basic Query:
>>>>>
>>>>> [image: Inline image 3]
>>>>>
>>>>>
>>>>> I hope this is what you were asking for...?
>>>>>
>>>>> Best,
>>>>> Greg
>>>>>
>>>>>
>>>>> On Thu, Feb 26, 2015 at 3:05 PM, Tran Chau (HISP Vietnam) <
>>>>> tran.hispvietnam@xxxxxxxxx> wrote:
>>>>>
>>>>>> Hi Greg,
>>>>>>
>>>>>> Can you give me more information about snapshots, your formulas, your
>>>>>> event cases, what the *Task strategy* is selected in *Schedule
>>>>>> automated aggregation* .... ?
>>>>>>
>>>>>> ..................................
>>>>>> Best regards,
>>>>>> Tran Chau
>>>>>>
>>>>>>
>>>>>>
>>>>>> On Thu, Feb 26, 2015 at 5:26 AM, Greg Rowles <greg.rowles@xxxxxxxxx>
>>>>>> wrote:
>>>>>>
>>>>>>> Hi Devs
>>>>>>>
>>>>>>> We've noticed our Aggregation-Queries are only loading values for
>>>>>>> the last month regardless of the selected time frame.
>>>>>>>
>>>>>>> Is there a known bug or known cause for this problem? Perhaps its a
>>>>>>> data-quality issue (we're still refining our data quality kinks, i.e. there
>>>>>>> may be programstageinstance.executiondate dates that violate expected
>>>>>>> values, e.g. date value "0013-02-13" and "0022-02-06" is present).
>>>>>>> Is this the likely cause? We cannot aggregate data before 24 Jan 2015...
>>>>>>>
>>>>>>> Greg
>>>>>>>
>>>>>>> --
>>>>>>> *Health Information Systems Program - South Africa*
>>>>>>> *- - - - - - - **- - - - - - - **- - - - - - - **- - - - - - - **-
>>>>>>> - - - - *
>>>>>>> Mobile  :    073 246 2992
>>>>>>> Landline:   021 554 3130
>>>>>>> Fax:          086 733 8432
>>>>>>> Skype:      gregory_rowles
>>>>>>>
>>>>>>> _______________________________________________
>>>>>>> Mailing list: https://launchpad.net/~dhis2-devs
>>>>>>> Post to     : dhis2-devs@xxxxxxxxxxxxxxxxxxx
>>>>>>> Unsubscribe : https://launchpad.net/~dhis2-devs
>>>>>>> More help   : https://help.launchpad.net/ListHelp
>>>>>>>
>>>>>>>
>>>>>>
>>>>>
>>>>>
>>>>> --
>>>>> *Health Information Systems Program - South Africa*
>>>>> *- - - - - - - **- - - - - - - **- - - - - - - **- - - - - - - **- -
>>>>> - - - *
>>>>> Mobile  :    073 246 2992
>>>>> Landline:   021 554 3130
>>>>> Fax:          086 733 8432
>>>>> Skype:      gregory_rowles
>>>>>
>>>>
>>>>
>>>
>>>
>>> --
>>> *Health Information Systems Program - South Africa*
>>> *- - - - - - - **- - - - - - - **- - - - - - - **- - - - - - - **- - -
>>> - - *
>>> Mobile  :    073 246 2992
>>> Landline:   021 554 3130
>>> Fax:          086 733 8432
>>> Skype:      gregory_rowles
>>>
>>
>>
>>
>> --
>> *Health Information Systems Program - South Africa*
>> *- - - - - - - **- - - - - - - **- - - - - - - **- - - - - - - **- - - -
>> - *
>> Mobile  :    073 246 2992
>> Landline:   021 554 3130
>> Fax:          086 733 8432
>> Skype:      gregory_rowles
>>
>
>
>
> --
> *Health Information Systems Program - South Africa*
> *- - - - - - - **- - - - - - - **- - - - - - - **- - - - - - - **- - - -
> - *
> Mobile  :    073 246 2992
> Landline:   021 554 3130
> Fax:          086 733 8432
> Skype:      gregory_rowles
>

PNG image

PNG image

PNG image

PNG image

PNG image

PNG image


References