[dhis2-devs] Incorrect dates in program report inside dashboard

 

Hi

We have an instance on which this date format has been selected ->"03-31-1981
(dd-MM-yyyy)". This has been done through settings->calendar in DHIS.

Now when I try to get a report in tracker dashboard , some dates are
incorrectly displayed.

This does not happen when date format is default(yyyy-MM-dd) but happens if
the format is changed to above(dd-MM-yyyy).

Have been able to reproduce on server : [https://play.dhis2.org/dev].
PFA screenshot.

Regards
harsh

Attachment: date bug Screenshot from 2016-02-16 16:49:42.png
Description: PNG image


Follow ups