Re: Expected "inter-stage" behaviour of ASSIGN program rule action

 

Hi Victor,
Sorry for the delayed response. 

The ASSIGN rules is only intended to affect the data that the user sees(the active/current event). This usually means that you can create helper fields, but they rely on the basis for your calculations being in the same event, or in previously registered data. The behavior you describe in 2.25 was not planned, and can be seen as a bug. 

There is two alternative options that can be pursued:
- Try creating a program indicator with analytics type "Enrollment"(introduced in 2.26). This will allow you to compare data from the latest event in each program stage across entire enrollments. Possibly this can take away the need for the helper fields.
- Make a helper field in second program stage, and make an assign rule that assigns "the other way". You will be able to query data from all other program stages when calculating and assigning values to helper fields.

Best regards,
Markus

> 22. mai 2017 kl. 16.32 skrev Victor Garcia <vgarciabnz@xxxxxxxxx>:
> 
> Hi all,
> 
> does anyone have any insight about this issue? It is fundamental to understand the behaviour of ASSIGN program rules in order to design the programs.
> 
> Thanks,
> 
> Víctor
> 
> On 15 May 2017 at 17:26, Victor Garcia <vgarciabnz@xxxxxxxxx <mailto:vgarciabnz@xxxxxxxxx>> wrote:
> Hi all,
> 
> I have a question regarding the behaviour of ASSIGN activity type in program rules when the program has several stages.
> 
> Our context is a program with three stages (opening, consultation, closure). In analysis we want to show data from opening and closure stages in the same table. Since currently it is not possible to do this kind of analysis in Event Report, we have created some ASSIGN program rules to copy values from closure stage to opening stage so that we have all the information we need for analysis in the same stage.
> 
> In 2.25 we saw that it was possible to assign values to previous stages and we created a setup relying on this behaviour. But it seems to have changed in 2.26 and now the ASSIGN action only affects the "active" stage and does not create any value in previous or following stages...
> 
> Since this point is not explicitely detailed in the documentation, we would like to know what is the expected "inter-stage" behaviour of ASSIGN in order to think about an strategy that will work in current and future releases. And if there is a way to do this kind of assignments in 2.26.
> 
> Thank you a lot,
> 
> Víctor
> 
> _______________________________________________
> Mailing list: https://launchpad.net/~dhis2-devs
> Post to     : dhis2-devs@xxxxxxxxxxxxxxxxxxx
> Unsubscribe : https://launchpad.net/~dhis2-devs
> More help   : https://help.launchpad.net/ListHelp


Follow ups

References