I've collected all the things I want to work on for 5.0 properly on
Launchpad now, assigned to myself. These are:

- Fix remaining UI/UX issues with the component selector.
- Investigate possible footprint preview panel locale issues
- Implement footprint selection tags on history items
- Document the new component selector.
- Fix OpenGL compatibility test crash on startup [1]
- Implement clean OpenGL/Cairo fallback [2]

Plus a few more minor things (all assigned to me on Launchpad).

I'd like to get all these done before 5.0, is that okay? I'm not sure
how far off the geometry library and via stitching are so I don't know
how much time that gives me.

[1] https://bugs.launchpad.net/kicad/+bug/1676915
[2] https://bugs.launchpad.net/kicad/+bug/1676916


On Tue, Mar 28, 2017 at 10:47:19AM -0400, Wayne Stambaugh wrote:
> Hey Chris,
> 
> The following items are holding up the v5 branch:
> 
> Symbol library table (me).
> Unified geometry library (Tom).
> Stitching via support (Tom & Orson).
> 
> I was hoping I would be done with the symbol library table by now but
> I'm really having trouble finding the time to finish it up.  I'm not
> sure where Tom and Orson stand.  I just saw an email from Tom the other
> day so it looks like there is still a bit of work to do on his end with
> the stitching via support.
> 
> Thanks,
> 
> Wayne
> 
> On 3/28/2017 10:45 AM, Chris Pavlina wrote:
> > Hey Wayne,
> > 
> > In the interest of prioritizing my own work - just curious if you have
> > any idea how long it's going to be before declaring the v5 feature
> > freeze, and what that's waiting on.
> > 
> 
> _______________________________________________
> Mailing list: https://launchpad.net/~kicad-developers
> Post to     : kicad-developers@xxxxxxxxxxxxxxxxxxx
> Unsubscribe : https://launchpad.net/~kicad-developers
> More help   : https://help.launchpad.net/ListHelp


Follow ups

References