On 24 Nov 2010, at 21:30, Mounir Bsaibes wrote:

> On Wed, Nov 24, 2010 at 2:49 PM, Jamie Bennett <jamie.bennett@xxxxxxxxxx> wrote:
>  * Use OpenProj [2] to setup the initial structure.
>    Why did you choose  OpenProj ? it does not seem  to have web interface. 
>     See: http://en.wikipedia.org/wiki/Comparison_of_project_management_software
>     I think first we need figure out which tool is best to use. 

Reasons are familiarity and the fact that this would be a pilot. To select the
right tool would require more effort than is necessary to just determine if we
can work with standard models. I'd like to keep it small and gather the pro's
and con's of using these tools before selecting a solution we could use in a
more wide-spread way.

>  * Work with the implementor(s) to define the requirements and gather timing
>   data at the beginning or the project.
>  * Regularly monitor the project against the requirements and timing data.
>  * Regularly produce a professional report on the progress of the project.
>  * Produce a post-mortem to determine if we would like to carry this on, with
>   or without improvements, to a further pilot project(s).
> 
> How does this sound to everyone else?
>    Sounds very good, as long as we don't impose a lot of overhead on the engineers.  

I see this as working with the engineer at the start to clearly identify the
requirements, a quick once-a-week call to be updated on the status (alternatively
the engineer could email the status) and a post-mortem at the end to see if it
was worth-while, very little overhead I feel.

Regards,
Jamie.