Hi,
On 12 May 2011 09:20, Mounir Bsaibes <mounir.bsaibes@xxxxxxxxxx> wrote:
> This method worked great for the WG's to assess what can reasonably be
> handled in the cycle.
> Currently, we use person/month to estimate the work needed at the TR level,
> we could have used person/week as well.
>
> https://spreadsheets.google.com/a/linaro.org/spreadsheet/ccc?key=t4KhKUVbaXkUl3TkGR6ngeg#gid=4
>
> Action done.
We need a prerequisite: an accurate list of the resources (person/team).
I'm trying to get the list of team member (in my case Platform) and my
current inputs aren't good enough:
- MeetTheTeam isn't up-to-date
- status.linaro.org (extract from team blueprints)
The teams are changing: new member, TL assignment, member leaving, etc...
Cheers,
Fathi