Plan for Work Tracking Tool
Hi,
I've sketched out a plan for selection a Work Tracking Tool (or tool(s) if necessary).
I've shared the Tool Spreadsheet to start gathering the requirements for the tool using the PM's for input.
Plan:
Week of May 16th (Week 20): Consider this the start of the Pilots and Evaluations
Week of May 23rd (Week 21): Gather PM's input. Get list of Tools being piloted into the spreadsheet (Vicky)
Week of May 30th (Week 22): or because of Public Reviews probably Week of June 6th: prioritize the list with the PM group. Socialize requirements with people like Kiko, David R., Joe Bates etc.
June 30th (Week 26): End of Pilot and Evaluations
Week of July 4th (Week 27): Update spreadsheet with Evaluation feedback. PM's propose a solution for August Gathering
Thanks for your input.
Regards,
Vicky Janicki