← Back to team overview

linaro-project-management team mailing list archive

Weekly Status report

 

Hi Joey,
You were present today during the release meeting when the issue about
status report was raised.
The concern from the release management is that the weekly status report is
not being looked at and may be a waisted overhead.
Instead, they prefer to replace the status review slot with a review of the
blueprints targeted for the milestone, checking whether these blueprints
have all what is needed for the release.

I think we should circle back and see how useful the weekly reports are, who
consumes them and how up to dates are kept.

It maybe that the release management / release management meetings are not
the only audience and we should keep them regardless of what the RM thinks.

In any case, it is a good idea to check back on this activity, whether to
continue with it or not.
If we can't resolve it through emails,  it maybe a good topic for the August
Connect meeting.

If we decide to keep doing it, we need to re-educate the TL's / PM's on how
it should be done, where on the wiki it should reside, etc.....

Thanks & Regards,
Mounir



-- 
Mounir Bsaibes
Project Manager