Re: Can we implement kiko's proposed roadmap flow by the next Connect? (was Re: Updated Roadmap to BP slide deck)
On Fri, 12 Aug 2011 10:57:31 +0200, Alexander Sack <asac@xxxxxxxxxx> wrote:
> When discussing the monthly model, I got feedback from techleads and
> PMs that they would like to keep a single page that tracks all the
> blueprints and work items for the upcoming milestones of all
> components the team participates in.
>
> This seems to be not included in current slidedeck/plan. Here a
> proposal that would give a team a single page to look at to track
> their progress for all upcoming deliveries.
>
> Proposal for Team Page:
> * current monthly milestone team page becomes a "upcoming milestones
> for team" page
Phrasing this as changes to a page, and then throwing away 90% of that
page makes this pretty hard to understand.
What you seem to be asking for is the following:
* For each team there will be a page for the current month.
* This will list "upcoming deliverables"
* Lists the blueprint, the assignee and the completion based on
workitems DONE.
* For each it lists the date at which it needs to be delivered and
the days left until that date.
* It also lists the component that is being delivered to.
- How do we map from blueprint to component?
* This page also lists workitems that are targeted to any milestone in
the month. This is sorted by target date, and then by importance. It
shows the assignee and the status as well as the description and a
link to the blueprint.
Given that I've estimated work so far to take up the time until the
Connect, and this isn't required for Connect planning, just useful for
execution afterwards, I'm not going to promise this before the Connect.
Thanks,
James