On Mon, Aug 29, 2011 at 3:56 PM, James Westby <james.westby@xxxxxxxxxx> wrote:
> Hi,
>
> Thanks for the feedback, responses inline.
>
> On Mon, 29 Aug 2011 15:36:35 +1200, Michael Hope <michael.hope@xxxxxxxxxx> wrote:
>> How does it scale when you have ~20 items?
>
> I've added 20 items so you can get an idea of that (assuming you meant
> the blueprint table)
>
> I also wonder what the lane view will look like with lots of cards, but
> we're expecting to see maybe 20 cards across all the states, so no
> section should get too large.
>
>> How is the priority shown?
>
> I forgot that, I added it now.
>
> I'm not sure if it should sort by priority first or milestone
> first. Hopefully they'll usually be the same order anyway :-)
Ah, I meant the how does the lane view look with a large number if
items, and how do the items show priority?