← Back to team overview

linaro-project-management team mailing list archive

Re: Roadmap cards template for Papyrs

 

On 13 March 2012 03:00, Mounir Bsaibes <mounir.bsaibes@xxxxxxxxxx> wrote:
> David,
> Looks good.
> The Work Packages is a new terminology, maybe a little more details about
> it.
> For example:  Work Package can be a Work Items block that can be delivered
> in one month.
> Some of the Working Groups use a single blueprint with multiple WI's blocks
> each WI's block to be delivered in one month.

I don't like adding new terminology.  A blueprint should be achievable
in a month and should be used instead of work item blocks.  Work
packages can be blueprint headlines - it doesn't matter that these
will be refined and perhaps split into the final blueprints as long as
there is tracability.

-- Michael


Follow ups

References