Re: FOR YOUR ACTION - 2012Q1 cards: updates needed

 

A reminder, for the TLs and PMs:

If you have not done so already, please remember to review cards, which
are targeted for 2012Q1, by Wednesday end-of-business and update

1- the engineering status update field
2- if the cards are marked as DEFERRED or DONE without a closeout
section then you should provide that also


You can see all the cards which have a fixVersion 2012Q1 using this JIRA
rapidboard - cards are categorised area by area on the horizontal lanes
http://cards.linaro.org/secure/RapidBoard.jspa?rapidView=5&quickFilter=30


Best regards,
Ilias

On 24/04/12 11:53, Ilias Biris wrote:
> Hello !
> 
> I have 2 action points for TLs and PMs who have cards in JIRA for
> 2012Q1. These cards can be checked in 1 JIRA board following the link
> http://cards.linaro.org/secure/RapidBoard.jspa?rapidView=5&quickFilter=30
> 
> Here is what I would like to ask you for:
> 1. Manual update of the card engineering status - every 2 weeks
> 
> While the connection of cards to blueprints is still ongoing (related to
> s.l.o work) there has to be a manual update of the status for the cards.
> 
> How to do this: edit a card, and update the "Engineering status update"
> field, with a concise comment indicating what is the ongoing status, any
> blocking issues, and the confidence that the card will be done before
> Connect@HongKong. You should summarise the work in progress instead of
> adding links to blueprints.
> 
> Frequency of updates: every 2nd Wednesday, starting from  next week
> (02May). It means that by Wednesday EOB all the status updates are in place.
> 
> I would like these updates for all cards which are actively being worked
> upon, even if they are  in Drafting state. If a card is not started
> simply note that in the engineering status update field and you are done
> until the work starts.
> 
> 2. Cards marked as DONE or DEFERRED should have a proper closeout section.
> 
> A template for the closeouts should be as follows
> 
> * In the case of DONE:
>  - How did you meet the acceptance criteria?  What did you deliver?
>  - How did you validate?
>  - How would you showcase this work?
>  - What went well?  What didn't go well?  What could we improve?
> 
> * In the case of DEFERRED:
>  - Why is the card deferred? Superseded by other cards, or is it
> obsolete due to other changes? Was there something delivered? What?
>  - Was there any validation done for any deliverables?
>  - Would the card need to be revisited for a new decision in the future?
> What should trigger such a review?
>  - What went well?  What didn't go well?  What could we improve?
> 
> Please check your DONE/DEFERRED cards and update the closeouts
> accordingly, by the end of this week.
> 
> As a closing remark: I have been preparing some wiki documentation for
> the usage of JIRA for the roadmap process. I expect the first draft out
> for your review by tomorrow latest. Please remember, you can ask your
> JIRA or roadmap related questions or file bugs as you encounter them through
> https://bugs.launchpad.net/linaro-roadmap
> 
> Best regards,
> 


-- 
Ilias Biris ilias.biris@xxxxxxxxxx
Project Manager, Linaro