Closing out cards for 2012Q1

 

Hello TLs/PMs

The cards for 2012Q1 should be completed by next week (before Connect).
For the list of cards which are targeted for 2012Q1 please see this
(hopefully familiar) rapidboard:

http://cards.linaro.org/secure/RapidBoard.jspa?rapidView=5&quickFilter=30


Could you make sure at latest by THU next week (24 May) that

a. 2012Q1 Cards have their closeout sections in place.

For a model on the closeout check
https://wiki.linaro.org/OPSCOM/RoadmapProcessWithJIRA#Delivering_a_card_-_what_to_do

Once you are ready with the closeouts, make sure you press the "Request
a Close-out" button at the top menu of each card closing out. If a card
is in any state BUT "Engineering", and yet it has finished, then please
talk to me or Loic to manage its transition to closeout review state in
JIRA.

b. Especially for cards which *will* have leftovers based on the
acceptance criteria: in their closeout section indicate what is the
missed content and propose what to do with the leftovers - ideally you
should already have card(s) in the pipeline to cover the missed content
in the coming quarter(s) if it is still important.

If in doubt what to do please ask questions!

Kind regards,
-- 
Ilias Biris ilias.biris@xxxxxxxxxx
Project Manager, Linaro
M: +358504839608, IRC: ibiris Skype: ilias_biris