maria-developers team mailing list archive
-
maria-developers team
-
Mailing list archive
-
Message #00766
Progress (by Knielsen): improving mysqlbinlog output and doing rename (39)
-----------------------------------------------------------------------
WORKLOG TASK
-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-
TASK...........: improving mysqlbinlog output and doing rename
CREATION DATE..: Sun, 09 Aug 2009, 12:24
SUPERVISOR.....: Monty
IMPLEMENTOR....:
COPIES TO......:
CATEGORY.......: Client-RawIdeaBin
TASK ID........: 39 (http://askmonty.org/worklog/?tid=39)
VERSION........: Server-9.x
STATUS.........: Un-Assigned
PRIORITY.......: 60
WORKED HOURS...: 29
ESTIMATE.......: 0 (hours remain)
ORIG. ESTIMATE.: 0
PROGRESS NOTES:
-=-=(Knielsen - Mon, 17 Aug 2009, 11:13)=-=-
Research and architecture review.
Worked 12 hours and estimate 0 hours remain (original estimate increased by 12 hours).
-=-=(Knielsen - Mon, 17 Aug 2009, 11:13)=-=-
Reported zero hours worked. Estimate unchanged.
-=-=(Psergey - Sun, 16 Aug 2009, 12:07)=-=-
Dependency created: 39 now depends on 49
-=-=(Psergey - Sun, 16 Aug 2009, 11:07)=-=-
Dependency created: 39 now depends on 46
-=-=(Psergey - Sun, 16 Aug 2009, 10:59)=-=-
Dependency deleted: 39 no longer depends on 46
-=-=(Psergey - Sun, 16 Aug 2009, 00:02)=-=-
Dependency created: 39 now depends on 47
-=-=(Psergey - Sun, 16 Aug 2009, 00:02)=-=-
Dependency created: 39 now depends on 46
-=-=(Psergey - Sun, 16 Aug 2009, 00:02)=-=-
Dependency created: 39 now depends on 45
-=-=(Guest - Fri, 14 Aug 2009, 15:52)=-=-
Title modified.
--- /tmp/wklog.39.old.11123 2009-08-14 15:52:29.000000000 +0300
+++ /tmp/wklog.39.new.11123 2009-08-14 15:52:29.000000000 +0300
@@ -1 +1 @@
-Replication tasks
+improving mysqlbinlog output and doing rename
-=-=(Guest - Mon, 10 Aug 2009, 16:32)=-=-
Adding 1 hour for Monty's initial work on starting the architecture review.
Worked 1 hour and estimate 0 hours remain (original estimate increased by 1 hour).
------------------------------------------------------------
-=-=(View All Progress Notes, 16 total)=-=-
http://askmonty.org/worklog/index.pl?tid=39&nolimit=1
DESCRIPTION:
A combine task for all replication tasks.
ESTIMATED WORK TIME
ESTIMATED COMPLETION DATE
-----------------------------------------------------------------------
WorkLog (v3.5.9)