[Bug 772654] [NEW] [6.0.2]Gantt view incorrect displays task end date
Devishree Brahmbhatt (OpenERP) (dbr-openerp) has assigned this bug to you for trunk:
System: Ubuntu 10.10. OERP 6.0.2. Fresh db, with Project and Long term
planning installed.
I made a new project with 45 hr/week Working time (9hr/day with 1 hour lunch time), starting at 25 April, 2011.
I made 2 tasks: Task1 (planned hour: 9 hr), Task2 (36 hr). Task2's parent is Task1.
Task Scheduler now computes OK (https://bugs.launchpad.net/bugs/768889,
https://bugs.launchpad.net/bugs/771161) the Task's Starting and Ending
date and time, and in Form view everything is OK.
But If I switch to the Gantt view the Task2's end date is not displayed correct.
Task2 starts correct at 26/04/2011 08:00 and should end 29/04/2011 18:00. But it ends 27/04/2011 20:00.
The problem is, that Task2's end date = start date+36hour, but the
working time is not taked in consideration.
Thank you.
Arpi
** Affects: openobject-client-web
Importance: Low
Assignee: OpenERP SA's Web Client R&D (openerp-dev-web)
Status: Confirmed
** Affects: openobject-client-web/6.0
Importance: Undecided
Status: New
** Affects: openobject-client-web/trunk
Importance: Low
Assignee: OpenERP SA's Web Client R&D (openerp-dev-web)
Status: Confirmed
--
[6.0.2]Gantt view incorrect displays task end date
https://bugs.launchpad.net/bugs/772654