Jay,
   Thanks for your helps. I finally found it in Other Info -> active Flag.
If I uncheck active checkbox, it will unlink SO with Packing Lists.

Thanks again

2010/9/3 Jay (OpenERP) <jvo@xxxxxxxxxxx>

> Hello Rogerer,
>
> The reference you point at is not the one which links sale order and the
> picking.
>
> You are looking at the right screen, but the tab is not the targetted
> one.
>
> You will need to go to the tab 'Other Info' and You will find the
> reference of sale order/purchase order. The reference is Many2one.
>
> Hope this helps.
>
> Thanks.
>
> --
> SO/PO should be allowed to be cancelled by un-linking the concerned
> packing!
> https://bugs.launchpad.net/bugs/596862
> You received this bug notification because you are a direct subscriber
> of the bug.
>
> Status in OpenObject Addons Modules: Fix Released
> Status in OpenObject Addons 5.0 series: Fix Released
> Status in OpenObject Addons trunk series: Fix Released
>
> Bug description:
> Hi,
>
>
> I just realized that with the new check on the last version it's just
> impossible to cancel a SO when his picking has already been confirmed !!!
>
> I mean, this should not appear in a normal flow, I agree, but what to do
> when you're facing this !??
>
> To reproduce :
>
> 1. Create a SO with 1 line (no matter the configuration)
> 2. Confirm it, go to the packing and confirmed it (force if necessary)
> 3. Go back to the SO, try to cancel => It says you must cancel the packing
> first !
> => Normal
> 4. Goto to the packing, you cannot cancel it, there is no button ! The
> workflow doesn't allow to cancel the "done" packing !
> => Can be normal...
> 5. Ok, so now you try to Delete this "done" packing in order to cancel your
> SO and it's not possible anymore !!! Says you cannot delete a done packing
>
> So, you cannot cancel, you cannot delete the packing... But you need one of
> those solutions to delete your SO !!
>
> We do need something here to be able to cancel the SO, whatever it is.
>
> I'll suggest to enable the workflow transition from Done to Cancel state
> into packing. Doing this, we'll be able to ensure who's doing that through
> "role" security.
>
> Thanks,
>
>
> Joël
>
> To unsubscribe from this bug, go to:
> https://bugs.launchpad.net/openobject-addons/+bug/596862/+subscribe
>

-- 
SO/PO should be allowed to be cancelled by un-linking the concerned packing!
https://bugs.launchpad.net/bugs/596862
You received this bug notification because you are a member of OpenERP
Manufacturing Experts, which is a direct subscriber.

Status in OpenObject Addons Modules: Fix Released
Status in OpenObject Addons 5.0 series: Fix Released
Status in OpenObject Addons trunk series: Fix Released

Bug description:
Hi,


I just realized that with the new check on the last version it's just impossible to cancel a SO when his picking has already been confirmed !!!

I mean, this should not appear in a normal flow, I agree, but what to do when you're facing this !??

To reproduce :

1. Create a SO with 1 line (no matter the configuration)
2. Confirm it, go to the packing and confirmed it (force if necessary)
3. Go back to the SO, try to cancel => It says you must cancel the packing first !
=> Normal
4. Goto to the packing, you cannot cancel it, there is no button ! The workflow doesn't allow to cancel the "done" packing !
=> Can be normal...
5. Ok, so now you try to Delete this "done" packing in order to cancel your SO and it's not possible anymore !!! Says you cannot delete a done packing

So, you cannot cancel, you cannot delete the packing... But you need one of those solutions to delete your SO !!

We do need something here to be able to cancel the SO, whatever it is.

I'll suggest to enable the workflow transition from Done to Cancel state into packing. Doing this, we'll be able to ensure who's doing that through "role" security.