obviosuly the calculation must be done for cost price and sale price to
be able to calculate the contribution at each level of BOM which is
crucial for decision making.

-- 
You received this bug notification because you are a member of OpenERP
Manufacturing Experts, which is a direct subscriber.
https://bugs.launchpad.net/bugs/702288

Title:
  Cost price calculation limited to 2 levels in product bom

Status in OpenERP Modules (addons):
  Invalid

Bug description:
  A concrete example better than a long and difficult explanation :-)

  We have the following product A composed of the product B and product B is composed from product C. So the below BOM:
  A
  -----B
  -----------C

  If the price of B is modified, then the price of A can be also modified.
  But if i modify the price of C, only B is modified and not A.

  This is a very important blocking issue, since in most of the real prod environment, we've of course more than 2 level of boms (in some customer installation, up to 100 levels !).
  So any modification at the bottom should have a consequence on all the bom structure until the top, else OpenERP cannot be used for production.