[Bug 726185] [NEW] long term scheduling doesn't work across projects
You have been subscribed to a public bug by Lorenzo Battistini - Agile BG - Domsense (elbati):
When you have two projects with two phases each. Every phase has two
tasks. You have only one the same resource for all tasks in both
projects. This resource is in Resource Allocation in all phases. And
user for the resource is a member of both projects. The resource-user
has Working period from standard demo data. So it is only one resource-
user for all 8 tasks. When you make "Compute Phase Scheduling" for all
projects the system schedules for the same time tasks from two projects
for the same resource-user. Scheduling works correctly only within
project. Scheduling doesn't see that resource-user is busy on another
project task.
** Affects: openobject-addons
Importance: Wishlist
Assignee: OpenERP R&D Addons Team 1 (openerp-dev-addons1)
Status: Confirmed
--
long term scheduling doesn't work across projects
https://bugs.launchpad.net/bugs/726185