[Bug 823838] Re: project hours don't include child projects hours
Hello Matteo,
We have tested the given scenario at our end and have found the
problem. And we have fixed the bug in Branch: lp:~openerp-dev
/openobject-addons/trunk-bug-823838-jam and have proposed for merging
and in lp:openobject-addons.
And Please ignore the Comment #1 , #2.
Thank You for your kind support.
** Branch linked: lp:~openerp-dev/openobject-addons/trunk-bug-823838-jam
** Changed in: openobject-addons
Status: Confirmed => In Progress
** Changed in: openobject-addons
Status: In Progress => Fix Committed
--
You received this bug notification because you are a member of OpenERP
Indian Team, which is subscribed to OpenERP Addons.
https://bugs.launchpad.net/bugs/823838
Title:
project hours don't include child projects hours
Status in OpenERP Addons (modules):
Fix Committed
Bug description:
On the project form the calculated field
Planned Time
has the following explanation: "Sum of planned hours of all tasks related to this project and its child projects."
But it seems that it only contains the sum of planned hours of all tasks related to the project
Test Case:
create a new db selecting "project" module from the setup wizard and
demo data
goto project / projects
the project:
Integrate a Sale and Warehouse Management has
planned time: 680
total time 0
time spent 0
progress 0
parent: Projects
I create a new Project: MyProj and change the parent project of Integrate a Sale and Warehouse Management to this one
planned hour form MyProj remains 0
create task MyTask for project MyProj
with Planned Hours 100
create a MyWork for MyTask with
time spent 50
mark MyTask as done
now MyProj has
planned time: 100
total time: 100
time spent: 50
progress 50%
completely ignoring the child project