[Bug 427733] Re: error with planed date on purchase order for product MTS
Hello
I encounter the same problem with date calculation in openERP 6.0.3
I agree with The description of Regis wrote on 2011-11-08
Gilles
--
You received this bug notification because you are a member of OpenERP
Indian Team, which is subscribed to OpenERP Addons.
https://bugs.launchpad.net/bugs/427733
Title:
error with planed date on purchase order for product MTS
Status in OpenERP Addons (modules):
Confirmed
Bug description:
Hi,
There is a problem with generated planed date on purchase order when a
manufacturing order want a product "make to stock" with 0 in stock.
(0 security days for this exemple)
When I sale today (september 11) a velo with delivery in 30 days to
customer (oktober 11), 3 days for manufacturing and I have 0
handelbars (MTS) in stock, this handelbar have 5 days from supplier to
me, OpenERP should generate a purchase order for this handelbar for
planed date 30-3 days = in 27 days (oktober 8), but the system
generates a planed date for today-5 days = there 5 days (september 6)
-> in the past !!!
It unusable for calculating supply in a production !!
- version 5.0.3 with JIT module -