← Back to team overview

openerp-india team mailing list archive

[Bug 940302] Re: Changing stock move scheduled date doesn't update related purchase order line scheduled date

 

Hello Nicolas ,

Before implementing this functionality  on OpenERP . We need  more
discussion on it  .So I am assigning it as opinion and ask suggestion
from our experts .

Thanks!!

** Changed in: openobject-addons
       Status: New => Opinion

-- 
You received this bug notification because you are a member of OpenERP
Indian Team, which is subscribed to OpenERP Addons.
https://bugs.launchpad.net/bugs/940302

Title:
  Changing stock move scheduled date doesn't update related purchase
  order line scheduled date

Status in OpenERP Addons (modules):
  Opinion

Bug description:
  - Create a PO
  - Go to corresponding generated IN > Edit it > edit the stock move line and change the scheduled date > Save
  = the expected date of the IN gets updated
  = but the scheduled date of the corresponding purchase order line isn't updated, and the expected date of the PO neither.

  If you want to modify a PO to keep your stock level forecast accurate
  (example you order some qty for week1 but then supplier is late and
  come back saying he will actually deliver less, and in week 4) it
  makes it complicated. You could just modify the stock move lines of
  course but then it doesn't relate to the PO anymore and If a user
  check the PO he'll be confused. I think they should stay sync.

To manage notifications about this bug go to:
https://bugs.launchpad.net/openobject-addons/+bug/940302/+subscriptions


References