Hello gregory,

I have tested your scenario, as per scenario It's a problem of stages.
and we should improve this things in kanbanview. That's why I am confirm
this Issue and assign to addons1 team.

Thanks!

** Changed in: openobject-addons
       Status: Incomplete => Confirmed

** Changed in: openobject-addons
   Importance: Undecided => Low

** Changed in: openobject-addons
     Assignee: (unassigned) => OpenERP R&D Addons Team 1 (openerp-dev-addons1)

-- 
You received this bug notification because you are a member of OpenERP
Indian Team, which is subscribed to OpenERP Addons.
https://bugs.launchpad.net/bugs/972544

Title:
  Kanban view - possible to link a task to any stages

Status in OpenERP Addons (modules):
  Confirmed

Bug description:
  On 6.1, in the form view it is only possible to move a task to a stage
  that is defined on the project of the task (and only to the stages
  defined on the project). Which is normal...

  BUT

  If you are on the Kanban view, it is possible to move a task to any
  stage because each stages are displayed on the screen. Which is
  incorrect.