[Bug 1006915] Re: Total timesheet is not correct with project_timesheet module
** Attachment added: "task work is not present in daily tab"
https://bugs.launchpad.net/openobject-addons/+bug/1006915/+attachment/3170176/+files/Screenshot-11.png
** Summary changed:
- Total timesheet is not correct with project_timesheet module
+ [6.1] Total timesheet is not correct with project_timesheet module
--
You received this bug notification because you are a member of OpenERP
Indian Team, which is subscribed to OpenERP Addons.
https://bugs.launchpad.net/bugs/1006915
Title:
[6.1] Total timesheet is not correct with project_timesheet module
Status in OpenERP Addons (modules):
New
Bug description:
Hi,
When I complete timesheet from a task work, hours are not include in [total timesheet]
The account is not present in daily tab but only in summary.
See screenshots.
It's with last runbot vs :
(Build 9787)
server (4185)
addons (6820)
web (2335)
Thx
Laurent
To manage notifications about this bug go to:
https://bugs.launchpad.net/openobject-addons/+bug/1006915/+subscriptions
References