[Bug 1016520] Re: long terme phase duration uom not taken into account
Hello,
Thanks for the quick response and nice video.
I have faced the same problem on French language in both 6.1 as well as
trunk (checked after fix on lp:1021194).
And that time phase scheduling taking a a days as a hours.
That's why I am confirming this issue.
Thanks !
** Summary changed:
- long terme phase duration uom not taken into account
+ long term phase duration uom not taken into account on French language
** Changed in: openobject-addons
Importance: Undecided => Medium
** Changed in: openobject-addons
Status: Incomplete => Confirmed
** Changed in: openobject-addons
Assignee: (unassigned) => OpenERP R&D Addons Team 1 (openerp-dev-addons1)
--
You received this bug notification because you are a member of OpenERP
Indian Team, which is subscribed to OpenERP Addons.
https://bugs.launchpad.net/bugs/1016520
Title:
long term phase duration uom not taken into account on French language
Status in OpenERP Addons (modules):
Confirmed
Bug description:
V6.1
Module project_long_term
If you set a duration in days in the phases, when you clic the
schedule phases button, the quantity of time is straightly taken as
hours instead of been first converted from days to hours and then sent
in hours to "faces"