← Back to team overview

openerp-india team mailing list archive

[Bug 1027795] [NEW] nbr. of days calculated by draging on the calendar view is wrong

 

You have been subscribed to a public bug:

On 6.1branch, didn't tested on trunk branch

In HR/leave request, If I drag span a few days on the calendar view, the
from_day and to_day on the 'leave' form is correct but the value on
"number of days" field is actual days + 1, while it will be correct if I
manually input the from_date and to_date value on the leve request form.

I assume it is a general error for web client not only for hr module.

** Affects: openobject-addons
     Importance: Medium
     Assignee: OpenERP R&D Web Team (openerp-dev-web)
         Status: New

-- 
nbr. of days calculated by draging on the calendar view is wrong
https://bugs.launchpad.net/bugs/1027795
You received this bug notification because you are a member of OpenERP Indian Team, which is subscribed to OpenERP Addons.