[Bug 1193814] Re: Tasks are not created on selected project stage

 

Hello,

I have checked the same scenario, when create a task with different
stage and than reload page. created task are stay on same stage.

Currently It's working fine in latest trunk and 7.0 also
Trunk (Build 27429)
server (5025)
addons (9039)
web (3910). 

I have attached screen cast as evidence.
so I assume that It's fixed in trunk. That's why I am set this bug as Fix Released.

Thanks!

** Attachment added: "Task create with selected project stage"
   https://bugs.launchpad.net/openobject-addons/+bug/1193814/+attachment/3947576/+files/task_stagenot_change.ogv

** Changed in: openobject-addons
       Status: Confirmed => Fix Released

-- 
You received this bug notification because you are a member of OpenERP
Indian Team, which is subscribed to OpenERP Addons.
https://bugs.launchpad.net/bugs/1193814

Title:
  Tasks are not created on selected project stage

Status in OpenERP Addons (modules):
  Fix Released

Bug description:
  Steps to reproduce:
  1. Go to Projects.
  2. Navigate to a specific project.
  3. Create a task on project stage which is not the first stage.
  4. Reload the page.
  5. See that the new task is created on the first stage, and not on the one you selected.

  I'm using Google Chrome, I also tested it with Safari.

  The OpenERP version is Version 7.0-20130620-231038.

To manage notifications about this bug go to:
https://bugs.launchpad.net/openobject-addons/+bug/1193814/+subscriptions