Comments to the plan for the next 2 weeks
Folks,
I uploaded the plan here:
https://drive.google.com/a/mirantis.com/?tab=mo#folders/0By295ZXYfjoGRENKZGRwLWwtdWc
Questions i propose to discuss:
1. Is it correct that by UC4: PCP RESOURCE USAGE you mean the following
reports that should automatically be sent to the licensing server (see
original version of SRS, e.g., 1.4.1):
VUS-10
Get usage report for total CPU quotas manageable under PA
Average limit during given reporting period
Expose in PCP the CPU available in PA
VUS-20
Get usage report for actual CPU count provisioned for PA tenants
Average usage during given reporting period
Expose in PCP the usage of CPU by the customers
VUS-30
Get usage report for total RAM quotas manageable under PA
Average limit during given reporting period
Expose in PCP the RAM available in PA
VUS-40
Get usage report for actual RAM count provisioned for PA tenants
Average usage during given reporting period
Expose in PCP the usage of RAM by the customers
VUS-50
Get usage report for total Storage quotas manageable under PA
Average limit during given reporting period
Expose in PCP the available storage in PA
VUS-60
Get usage report for actual Storage count provisioned for PA tenants
Average usage during given reporting period
Expose in PCP the usage of Storage by the customers
2. How will you be able to finish this UC4 by next week if UC9 won't be
done by that moment?
3. Is it correct that an access to OpenStack will be provided via one of
the screens in UC9?
4. Re the timelines, i would prefer to see UC4, UC7 and UC8 finished by
next Tue, Oct, 7th, so you will be able to demo it during our weekly call.
Let's discuss it.
Thanks.
--
Regards,
Evgeniya
Mirantis, Inc
Mob.phone: +7 (968) 760-98-42
Email: eshumakher@xxxxxxxxxxxx
Skype: eshumakher